July 26, 2024
THE NORTH EAST: 27TH MAY TIMELINE AND TODAY’S TOWER COLLAPSE INCIDENT
– By Ayomide Oginni

Kindly Share

Facebook
Twitter
LinkedIn
WhatsApp

THE NORTH EAST: 27TH MAY TIMELINE AND TODAY’S TOWER COLLAPSE INCIDENT

… as other vandalism incidents collapse three towers along Biu-Dambua 132kV and remove tower members on one tower along Makurdi-Jos 330kV transmission line

The transmission Company of Nigeria, TCN hereby states that tower number T290, one of the four new towers erected by TCN contractors along the Jos – Gombe 330kV transmission line collapsed during the cable stringing process.

The incident occurred at about 7am, this morning, 27th May, 2024, while the contractor was stringing the cable on the last tower, which was supposed to enable the final jointing of the power cable in time for energizing of the line today.

Despite of the security challenges in the area, TCN contractors and some of our engineering staff worked tirelessly to fast-track the project, doing all that was humanly possible to meet the time-line. Daily, the contractor, TCN engineers accompanied by security operatives consistently left the site by 10pm in the night and resumed work at 6am every day.

Constructing towers and stringing power cables at such heights is highly technical, although TCN contractors and staff have successfully completed similar projects in other parts of the country. The collapse of the fourth tower is a significant setback, given the extensive efforts to ensure that today’s power restoration timeline was met.

Our contractor is currently dismantling the collapsed tower members, to enable its reconstruction and final restringing of the cable.

It is unfortunate to note that while TCN is working on reconstructing and restringing the four vandalised towers, three (3) towers along the Biu – Danbua 132kV transmission line were also vandalized with 16 spans of conductors stolen. The towers, which have all collapsed include towers T1690, T1691 and T1692. TCN has mobilized a contractor to commence their reconstruction. This discovery was made by TCN patrol team, last Friday.

Additionally, this morning, the TCN lines patrol team discovered that tower T540 along the Makurdi – Jos 330kV double circuit transmission line has been vandalised. Sections of the tower have been removed, although the tower remains standing. TCN has contracted emergency repairs, to prevent its collapse.

We reiterate our commitment to restoring normal bulk power supply through the distribution companies serving the North East and other areas affected by vandalism. There is however an urgent need for everyone to join hand with TCN in protecting our collective assets by being vigilant and reporting any suspected acts of tower and line vandalism promptly.

Ndidi Mbah
GM, Public Affairs
27/5/24

Kindly Share

Facebook
Twitter
LinkedIn
WhatsApp

Copyright @ TheDaily. All rights reserved. This material, and other digital content on this website, may not be reproduced, published, broadcast, rewritten or redistributed in whole or in part without prior express written permission from TheDaily

Leave a Comment

Your email address will not be published. Required fields are marked *

📰 Subscribe to our Newsletter

Scroll to Top